Consulting Services for Independendent Engineering Services for 4 / 6 Laning of Delhi / Haryana border to Rohtak section of NH-10 in the state of Haryana on BOT basis under NHDP – Phase III A


...

Project Details

Title:

Client:National Highways Authority of India

Duration: 36 months

Cost:4860 million

Project Description

The Consultancy Services of Independent Engineer are required for 4 / 6 laning of Delhi / Haryana Border to Rohtak on N.H. 10 from km 29.70 to 87.00 including construction of Bahadurgarh and Rohtak Byepass on B.O.T. basis. • Project Length is 63.49 km with total Project cost of Rs. 486.00 Crores. • The duration of the project is 36 months which includes 27 months for Construction Supervision and 9 months for Defect Liability. • The work constitutes upgradation involving construction of 4 / 6 Lane Highways including Bridges, widening and rehabilitation of bridges and culverts, construction of high embankments / elevated structures / ROBs, wayside amenities etc. along existing highways. • The construction works involve use of modern equipment and construction practices / techniques. • The services of Independent engineer apply to construction, operation and maintenance of six / four Lane project Highway.(Length-63.49 km. - 4 / 6 lane)